← Older posts

Direct Access Cap for 2013 in California filled in less than 45 Seconds

In an initial report requested by industry groups, the Energy Division of the California Public Utilities Commission released the results of the January 13, 2012 Direct Access enrollment.   This enrollment represents the limited phase-in of direct access stemming from Senate Bill 695.  The results are eyepopping.

A lucky 141 customers jumped from utility service to receiving service from direct access providers, representing just over 1250 GWh of load.  By 9 AM, the utilities had already rejected 12,730 customers.

Just 45 seconds into the enrollment period completing the final phase-in of direct access, the annual cap was already completed among all three large investor-owned utilities.  In PG&E’s service territory, the cap was filled in 1 second.

However, it appears that both PG&E and SCE did not accept as much load as it should have.  PG&E only accepted load of 356 GWh, while having 392 GWh left of cap room.  Similarly, SCE only accepted load of 680 GWh, while having 1,027 GWh left of cap room.  SDG&E actually accepted slightly more than it should have: 220 GWh while only having 218 GWh of cap room left.

It is unclear how these discrepancies will play out.

Here’s the chart from the Energy Division’s initial report:

Results of the January 13, 2012 DA Enrollment

All load in annual GWh

Ln#

PG&E

SCE

SDG&E

1 No. of Accepted Customers

22

74

45

2 Accepted Load (annual GWh)

356

680

220

3 DA Load as of 3/31/2012

9,128

10,683

3,344

4 Overall 2013 Load Cap

9,520

11,710

3,562

5 Line 4 – Line 3

392

1,027

218

6 No. of Rejected Notices Before 9 AM

7,806

2,713

2,211

7 No. of Rejected Notices After 9 AM

13,059

15,521

402

8 Time to Fill Year 3 Cap (min/sec)

0/5

0/47

0/18

9 Time to Fill Year 4 Cap (min/sec)

< 0/1

0/45

0/6

10 No. of Accepted Customers – no DASR Y1

37

115

9

11 Accepted Load – no DASR Y1

128

581

17

12 No. of Accepted Customers to TBS Y2

38

78

2

13 Accepted Load to TBS Y2

55

208

1

14 No. of Accepted Customers to TBS Y3

18

29

3

15 Accepted Load to TBS Y3

37

162

1

FERC Asks: When Does a Generation Developer Become a Transmission Provider?

This blog post comes from my DC colleague Margaret Claybour. Generation developers on the West Coast should take special note as the FERC orders described in this blog all involve facilities out West.

——————————

When an unwary generation developer builds a tie-line to the nearest transmission line, it might assume that the use of that line can be wholly dedicated to moving power from its generation facility to the grid.  But that assumption would be incorrect.  With the stroke of a pen (or a computer keystroke), a third-party can transform the generation developer into a transmission provider simply by requesting interconnection to that generation tie line.  When that happens, the generation developer instantaneously becomes subject to FERC’s open access rules, the same rules usually reserved for transmission-owning public utilities, including the requirement to file an open access transmission tariff (OATT).

On April 19, FERC issued a Notice of Inquiry (NOI) asking for help in applying this policy.  Developers and others should consider speaking up.

FERC’s Current Policy

Under FERC’s current priority rights policy, there are three instances in which the owner of generator interconnection facilities can reserve priority rights to capacity on its line:  (i) for its “existing use” at the time of a third party request for service; (ii) for future use based on “specific, pre-existing generator expansion plans with milestones for construction of generation facilities” for which the owner can demonstrate that it has made “material progress toward meeting those milestones” that pre-dates a third party request for service; and (iii) for use by an affiliate that can meet the “specific plans and milestones” standard and to whom ownership of the interconnection facilities will be transferred.  FERC’s first articulated the “specific plans and milestones” standard in 2006 in its Aero Energy, LLC order.  Arguably, it wasn’t until 2009, in Milford Wind Corridor, LLC, that FERC provided some clarification of how a developer can satisfy the standard.  Even so, as we’ve seen in Terra-Gen Dixie Valley, LLC, what qualifies as “specific plans and milestones” still isn’t clear.  FERC’s priority rights policy borders on a “we’ll know it when we see it” approach, which does not leave a generator developer with much certainty.

Even if a generation tie line owner is able to secure priority rights for itself or its affiliates on its interconnection facilities, the OATT filing requirement still looms.  Under FERC’s current policy, a “valid” request to interconnect from an unaffiliated third party triggers the requirement to file a pro forma OATT within 60 days of the request, whether or not priority rights exist.  The generator is thereby forced to divert staff and financial resources to develop and maintain an OATT.  And while FERC typically grants waiver of several provisions in the pro forma that clearly do not apply to transmission service on a generation tie line, for example, network transmission service, the generator’s OATT must include potentially onerous provisions, such as transmission planning and calculations for available transfer capabilities.

As my colleague Brian Gish discussed in his advisory on the subject: generation tie line owners also can be required to comply with NERC’s mandatory electric reliability standards for transmission facilities, in addition to the bevy of reliability obligations required for Generator Owners and Generator Operators.  This, too, can tax a generator’s financial and personnel resources.

What FERC’s Looking for in its NOI

Through the NOI process, FERC is seeking comments on “alternative approaches to govern third-party requests for service and priority rights.”  Considerations on the table include: use of a modified OATT, including a safe harbor period during which a third party may not submit interconnection requests to the generation tie owner; and in lieu of the OATT framework, use of the large generator interconnection procedures, permitting the parties to mutually agree to use of and compensation for the facilities.

Notably missing from the NOI is discussion of the NERC implications of a generation tie line being used to provide transmission service.  We’ll have to await the outcome of NERC’s ongoing Project 2010-07, which involves proposed changes to generator requirements at the interface with the transmission grid, to get, hopefully, some clarity regarding the reliability obligations of generation owners and generation operators.  Stay tuned.

NOI comments are due June 11, 2012.

FERC Asserts Jurisdiction Over Certain Sales of Renewable Energy Credits

Jim Mitchell of our DC Office provides the following report:

The Federal Energy Regulatory Commission ruled last week that the sale of renewable energy credits (“RECs”) as part of a bundled transaction that also includes the sale of electricity is subject to its regulatory jurisdiction under Part II of the Federal Power Act.  However, the unbundled sale of RECs in a transaction that is independent of a wholesale electric energy transaction is not subject to FERC jurisdiction.

Earlier this year,  WSPP, Inc. (formerly, the Western Systems Power Pool) applied for authorization to establish a new service schedule for sale of RECs as part of the WSPP Agreement on file at the FERC.  WSPP asked the FERC either to confirm that it lacks jurisdiction over the sale of unbundled RECs, or to provide advice on how WSPP should proceed in the event that the FERC has such jurisdiction.  In the recent order on RECs, the FERC found that when a transaction is a bundled transaction that includes both the sale of electricity at wholesale (which is clearly subject to FERC jurisdiction) and the sale of RECs, the price at which the RECs are sold may affect the price of electricity.  For that reason, the FERC concluded that it “has jurisdiction over the wholesale energy portion of the transaction as well as the RECs portion of a bundled REC transaction under FPA sections 205 and 206 (regardless of whether the contract price is allocated separately between the energy and RECs).”   The FERC further ruled that it has jurisdiction over the sale of RECs that are sold in conjunction with a wholesale electricity sale, even if the sale of RECs and the sale of electricity are the subject of separate agreements.  The order states, conversely, that “when an unbundled REC transaction is independent of a wholesale electric energy transaction, … the unbundled REC transaction does not affect wholesale electricity rates, and the charge for the unbundled RECs is not a charge in connection with a wholesale sale of electricity.”

The order leaves for future determination the manner in which the FERC will regulate the sale of RECs when they are being sold as part of a bundled transaction.  Among the issues that presumably will need to be resolved are:  (1) where the electricity is being sold at cost-based rates, how will he FERC will determine the costs of the RECs that are included in a bundled transaction?   (2) how will the FERC regulate the bundled sale of RECs when electricity is being sold pursuant to a market-based rate power sales tariff.  (3) will the FERC assert jurisdiction over the bundled sale of RECs by Qualifying Facilities whose wholesale electricity sales have been exempted from regulation under the Federal Power Act?   Additional FERC guidance may be needed to resolve these issues.

Fire Safety Proceeding Continues Into Phase 3 at the California Public Utilities Commission

Commissioner Simon and Administrative Law Judge Kenney presided over a prehearing conference in the Commission’s fire safety proceeding (R.08-11-005) today.  The usual players were in attendance– the electric utilities, the communication utilities, consumer groups, environmental groups, and a few new players from the fire safety community (CalFIRE and LA Fire).

Today’s topic was to determine the scope of Phase 3.  Items that will certainly be included in Phase 3:

1) the detail and amount of reporting by the electric utilities on fires or other events that occur on their power lines;

2) revising the construction and strength requirements for power-line and aerial communication facilities.

The big question today was on what sort of maps should be used/created to assess fire risk and to determine inspection cycles.  Another important question that will be determined by the Commissioner’s scoping memorandum that will be issued soon is what uses the Commission envisions coming from the map.

Commissioner Simon hinted at the hearing that he saw a broader vision for the use of the maps beyond just identifying fire risk.  He appears to be leaning towards developing maps that identify the amount of available biomass in certain areas that could then be used to site potential biomass facilities around the state– an interesting idea, but not exactly what the majority of the parties at the hearing envisioned coming out of this proceeding or being within the scope of Phase 3.

Should be an interesting proceeding that may have ramifications not only in California, but in other states and countries where fire safety is of paramount importance.

 

New Director of the Consumer Protection and Safety Division of the California Public Utilities Commission

The California Public Utilities Commission (CPUC) announced a new director of the Consumer Protection and Safety Division (CPSD).  The former director was reassigned after the San Bruno tragedy and CPSD has been without a director for a number of months now.

The search for a director was difficult as it was generally limited to others currently in state service AND former and current members of the armed forces.  As it turns out that limited exception for veterans proved invaluable as the military is where the CPUC found its guy:  Brigadier General Jack Hagan.

General Hagan retired from active duty in 1999, but was recalled to duty to train military and civilian subject matter experts to respond to terrorist attacks in California.  Though not a direct connection to the sort of work that he will be doing at CPSD, one can see why the CPUC thought a 28-year Marine with 15 years of command experience might be the right man for a job.

No matter what, having a permanent fixture at the helm of CPSD should change the safety culture at the CPUC.

Full press release about General Hagan can be found here.

 

 

First Auction of Greenhouse Gas Emission Allowances Delayed by California Air Resources Board

Important news from the Air Resources Board.

Mary Nichols, Chair of the California Air Resources Board, announced at a state Senate panel yesterday that the first auction of greenhouse gas emission allowances would be delayed by 3 months and held in November.  This makes sense as no protocols regarding how the auction would be conducted have been released as of yet.

Mary Nichols did state that the California Air Resources Board does intend to hold a “practice auction” in August.  The practice auction in August is meant to give covered entities (companies that actually will have to purchase these greenhouse gas allowances) an opportunity to see how the system will actually work.

Since the compliance obligations do not actually go into effect until 2013, pushing back the first actual auction should not cause any real delays to the implementation of the cap and trade program overall.  But the need to delay the initial auction does speak to the difficulties of implementing the cap and trade program.

Given the complexity in the program, it likely makes sense for covered entities to participate in the practice round and get their feet wet.

California Court finds Renovated Ferry Building to No Longer Be Municipal Load

Ferry Building

The Ferry Building in San Francisco

A California Appellate Court confirmed on March 27 an earlier Superior Court ruling that the iconic Ferry Building in San Francisco, a property owned and originally largely occupied by the Port of San Francisco, was no longer Municipal Load.

This is significant because the City and County of San Francisco has a contract with Pacific Gas and Electric Company (PG&E) that distinguishes between City-generated electricity at its hydro plant in Hetch Hetchy to be used for municipal purposes (Municipal Load) and electricity to be used for commercial purposes.  Originally, the power used by the Ferry Building was considered to be Municipal Load.

However, PG&E has successfully argued that the use of the Ferry Building, post-renovation in 2003, has materially changed and so no longer qualified as Municipal Load.

The court agreed that the post-renovation account was no longer Municipal Load and granted declaratory relief in favor of PG&E.  The trial court will now consider what damages may be due to PG&E under a breach of contract claim.

Proposed Decision Adopting Metrics to Measure Smart Grid Deployments

The California Public Utilities Commission released a much awaited proposed decision  on March 20th regarding metrics to measure the deployment of the smart grid in the PG&E, SCE, and SDG&E service territories.

The consensus metrics can be found in Attachment A to the proposed decision.   The consensus consists of 19 metrics that the utilities will report on as part of their annual reports.

Specifically, the metrics are related to Customer/AMI metrics; plug-in electric vehicle metrics; storage metrics; and grid operations metrics.

The Decision does establish 4 technical groups to address

1) updates or revisions to the metrics adopted herein, if needed;
2) the creation of metrics related to cyber-security;
3) the creation of metrics related to environmental
benefits; and,
4) the creation of broad goals to focus all stakeholders toward a
common vision.

Opening Comments on the proposed decision are due Monday April 9.  Reply comments on the proposed decision are due Monday, April 16.

 

 

Check out DWT’s latest blog site!

DWT launched its Northwest Energy and Environmental Law Blog today.  Check it out for all the latest news and analysis from the best and brightest at DWT!!

PG&E Unveils Customer Data Access Project

PG&E filed an application at the California Public Utilities Commission requesting $19.4 million to fund the project to provide third parties with access to a customers’ electricity usage data (when authorized by the customer) as part of its Customer Data Access Project.

Following the Commissioner’s earlier decision regarding  privacy and security restrictions on customer data, PG&E proposes a customer verification process that will require affirmative confirmation from customers authorizing third parties access to their electricity usage data, as well as specific specifications regarding the scope and duration of such third party access.

The Customer Data Access Project is obviously an important step in the quest for a smart grid in California, and another set of costs incurred by customers in order to make the smart grid a reality, so all those companies seeking to use energy data in their products should pay close attention to how PG&E’s application moves forward.

← Older posts